Bombay Railway Engineering Co. v. General Manager , C.R.
Case brief
What is this about?
The High Court dismissed an appeal challenging an arbitral award where the arbitrator had declined certain compensation claims. The court held that a specific prohibitory clause in the contract barred claims for damages or compensation despite delays, following Supreme Court precedent. The appeal was dismissed as no case for interference was made out.
What did the court decide?
The appeal was dismissed. There shall be no order as to costs.