Vardhman Developers Limited v. Union of India and Ors.
Case brief
What is this about?
The High Court allowed partial construction of 11,000 sq.m for municipal school, staff quarters, and rehabilitation pending environmental clearance, directing the Authority to consider the project expeditiously upon an undertaking from the developer.
What did the court decide?
Allowance to construct 11,000 sq.m for municipal school, quarters, and rehabilitation; direction to Respondent No.4 to consider application expeditiously upon filing of an undertaking.