What is this about?
This is a short order from the Nagpur Bench of the Bombay High Court regarding a first appeal. The court stayed the execution of an impugned award dated 24.11.2010, conditional upon the appellant depositing the entire awarded amount within ten weeks, rejecting the submission for a 50% deposit.
What did the court decide?
Stay of execution of the award dated 24.11.2010 is granted on condition that the appellant deposits the entire award amount within ten weeks.