Srimauli Infastructure Pvt. Ltd. v. State of Mah and Ors.
Case brief
What is this about?
Civil Application withdrawn because the underlying Arbitration Application was withdrawn, resulting in the disposal of the present application.
Civil Application withdrawn because the underlying Arbitration Application was withdrawn, resulting in the disposal of the present application.
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY, APPELLATE SIDE, BENCH AT AURANGABAD.
District : Latur
Civil Application No. 5773 of 2011 (In Arbitration Application No. 7 of 2010) (Srimauli Infrastructure Pvt. Ltd., Pune, through Shri Nandkishor s/o. Purushottam Goud, employee and power of Attorney Holder, R/o. Chhaoni, Aurangabad. Vs.
The State of Maharashtra, through its Principal Secretary, Public Works Department, and 3 others)
Appearances : Mr. G.N. Kulkarni, Advocate, holding for Mr. A.M. Karad, Advocate, for the applicant. Mr. P.G. Deshmukh, Special Counsel, for respondent nos.1 to 4.
CORAM : B.P. DHARMADHIKARI, J. DATE : 15TH JUNE 2012
COURT'S ORDER :
In view of disposal of Arbitration Application No. 7 of 2010, as withdrawn, present Civil Application does not survive and the same is disposed of.
(B.P. DHARMADHIKARI) JUDGE ............................ bgp/ca5773
Srimauli Infrastructure Pvt. Ltd.
The State of Maharashtra
B. P. Dharmadikari
As recorded by the court registry