V.I.D.C. Thr. Exe. Engineer v. Gulab Ashru Kakde and 2 Ors.
Case brief
What is this about?
The High Court of Judicature at Bombay, Nagpur Bench condensed delay in Civil Applications, allowing them. On first appeals arising from land acquisition awards, the Court modified judgments, reducing compensation to Rs. 1,00,000 per hectare (without statutory benefits) and permitted the appellant to withdraw excess amounts.
What did the court decide?
First Appeals partly allowed; compensation fixed at Rs. 1,00,000 per hectare with statutory benefits; Appellant allowed to withdraw excess amount.