This judgment appoints a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 for a dispute regarding a building water proofing contract. The court held that the right to appoint an arbitrator is forfeited once a Section 11(6) application is instituted in Court.
What did the court decide?
Appointment of Shri Justice B.N. Naik, Former Judge of this Court, as the sole arbitrator under the Arbitration and Conciliation Act, 1996.