2. An area of 2 Hectare from Gat No.349 of
the claimants/respondents was acquired for Minor
Irrigation Tank, Kalambwadi. The Special Land
Acquisition Officer awarded Rs.18,000/- per
hector after classifying the land in four groups
of seasonal bagayat lands. The grouping depended
on the land revenue. For Group I, compensation
was at Rs.7800/- per hector; for Group II it was
at Rs.9000/- per hector; for Group III it was at
Rs.10500/- and; for Group IV it was at
Rs.12000/- per hector. The Reference Court found
that this classification and grouping was not
proper. If Rs.12000/- per hector was given as
maximum compensation, then, according to the
Reference Court, the claimants were entitled to
additional amount of Rs.6000/-. On and above the
claimants were also paid additional compensation
of Rs.3360/- and Rs.1800/- as solatium. The
approach of the reference Court is proper. It is
not unjust. In the circumstances, therefore,
there is no merit in this appeal. The same is
dismissed. No order as to costs.