The Special Land Acquisition Officer treated the
land as Jirayat land and awarded compensation at
the rate of Rs.15,300/- per hectare for
cultivable land and Rs.200/- per hectare for 6R
potkharaba land. Therefore, a reference came to
be filed at the instance of the claimant. The
Reference Court found that the classification of
the land as Jirayat land was not proper, because
the crops statements from 1982-83 to 1990-91
reveal that the claimant had taken crops from
irrigation. So far as basic price is concerned,
the claimant examined and proved Exhibit 22. It
was in respect of 27R of land for Rs.57,000/- and
after deducting Rs.7000/- as the price for 4/5
mango trees the court concluded that Rs.30000/-
was the proper price. This sale deed was of
1984. The notification under Section 4 was two
years after . Therefore, 10% escalation was
awarded and the compensation was fixed at
Rs.36,000/- per hectare. The reference court had