FPA-PMLA-1395/MUM/2016 of Godavari Corporation Pvt. Ltd. v. The Deputy Director Directorate of Enforcement, Mumbai
Case brief
What is this about?
The Tribunal dismissed four appeals filed against the confirmation of provisional attachment orders under PMLA. The appellants argued that amendments imposing a 90-day limit for filing prosecution complaints should apply retrospectively, making the attachments illegal due to delay. The Tribunal held the amendment was prospective, the complaint was filed within the valid period from the amendment d
What did the court decide?
The appeals were dismissed and disposed of along with pending applications.