FPA-FE-78/MUM/2010 of M/s. Baba Rayon Fabrics (P) Ltd. v/s The Special Director, Directorate of Enforcement, Mumbai
Case brief
What is this about?
The Appellate Tribunal rejected a plea for a stay on the full pre-deposit of penalty under FEMA. Noting the appellants had advanced and secured loans despite losses, the Member ruled 'undue hardship' was not proven. However, directing payment of fifty percent within sixty days deemed sufficient to meet the ends of justice.
What did the court decide?
Directed payment of fifty per cent of the total penalty of Rs. 29,00,000/- within sixty days of the order, failing which the appeal would be dismissed.