Appeal No. 95 of 2020 of Haldia Energy Limited v. West Bengal Electricity Regulatory Commission
Case brief
What is this about?
The Appellate Tribunal allowed the appeal in part, holding that directives by KoPT and DGS causing a material change in project scope constitute a 'change in law' event mandating pass-through of costs. The Tribunal remanded for re-examination of tax variation claims and RoW expenditure, while upholding the allowability of costs for unprecedented rainfall events.
What did the court decide?
Remanded to State Commission to allow pass-through of costs for change-in-law events (JUB overstay, additional work), re-examine tax variation and RoW claims, and allow head-loading/approach road cost