Appeal No. 141 of 2023 & Ia No. 1786 of 2024 & 1629 of 2022 of Haldia Energy Limited v. West Bengal Electricity Regulatory Commission
Case brief
What is this about?
Appeal against the West Bengal Electricity Regulatory Commission's order disallowing specific construction costs. The Tribunal allowed claims for domestic BTG procurement, flood-related BoP costs, and safety-compliance intake water costs, partially allowed enabling works and overheads, and allowed the full IDC claim.
What did the court decide?
Allowed: Domestic procurement (Rs. 5.9 Cr), Flood costs (Rs. 11.5 Cr + Rs. 5.9 Cr), IDC (Rs. 82.5 Cr), Enabling works increase (Rs. 15 Cr), R&R increase (Rs. 0.9 Cr), and Overheads (Rs. 44.1 Cr). Reje