Appeal No. 66 of 2017 of Tangedco v. Central Electricity Regulatory Commission & Ors.
Case brief
What is this about?
TANGEDCO appealed against CERC's order allowing tariff socialization for NP Kunta Solar Park transmission assets. The Tribunal held that lines owned by the Central Transmission Utility are ISTS under Section 2(36)(iii) regardless of intra-state consumption and barred the appeal res judicata.
What did the court decide?
Affirmed the order dated 30.06.2016 passed by CERC in Petition No. 26/TT/2016 dismissing the appeal of TANGEDCO.