Appeal No. 204 of 2016 of Aravali Power Company Private Limited v. Haryana Power Purchase Center (Hppc) & Ors.
Case brief
What is this about?
The Appellate Tribunal allowed an appeal challenging the Commissions calculation of Scheduled Commercial Operation Dates. The Tribunal held that while calculating from the main plant award date was correct, the specific months cited in the investment approval were erroneous. It directed remand to determine SCOD based on the feasibility report timeline of 45 months. Result: Partially Allowed.
What did the court decide?
The impugned order is set aside to the extent said. The case is remanded to the Commission to determine timelines afresh based on the Feasibility Report schedule within four months.