first six months of FY 2013-14, as given in Table 6.16. The price of coal and oil has been considered by increasing the above validated values by 5%, to account for change in price during FY 2014 15. In Tariff Order for FY 2013-14, the Commission had decided to consider the calorific value of coal as per Orders of the Commission dated 08.10.2012 & 27.02.2013, for working out the fuel cost from November, 2012 to March, 2013, FY 2013-14 and onwards, i.e. calorific value (GCV) of receipted coal minus maximum permissible drop of 150 kCal/kg in calorific value (GCV). In para 5.8.1 of this Tariff Order, the Commission, while carrying out the Review of FY 2013-14, has considered the calorific value of coal as per Orders of the Commission dated 08.10.2012 & 27.02.2013, for working out the fuel cost for FY 2013-14. CERC in its Tariff Regulations, 2014 has considered the gross calorific value of coal as received, for working out the energy charges (fuel cost) in respect of coal based thermal stations. The Commission accordingly decides to consider the gross calorific value of received coal for working out the fuel cost for FY 2014-15. The figures of gross calorific value of coal as given in column III of Table 6.16 are gross calorific values of coal as received, as validated by the Commission for the period from April, 2013 to September, 2013. The price and calorific value of coal indicated above are the weighted average values of coal, including PANEM coal.”