A.No. 159 of 2015 & Ia No. 255 of 2015 of Sri Avantika Contractors (I) Limited v. Bihar Electricity Regulatory Commission & Ors.
Case brief
What is this about?
The Appellate Tribunal for Electricity allowed the appellant's appeal against the Bihar Electricity Regulatory Commission's order rejecting a time extension for achieving the Commercial Operation Date (COD). The Tribunal found the delay was caused by the Second Respondent's failure to cooperate regarding funding and evacuation infrastructure approvals, extending the COD deadline to the actual achi
What did the court decide?
Extension of time for COD granted until 31.01.2016; appeal allowed; second respondent ordered to pay differential tariff and carrying costs.