A.No. 48 of 2022 of Balaji Naik a. v. Gulbarga Electricity Supply Company Limited. & Anr.
Case brief
What is this about?
The Tribunal dismissed the appeal filed by a solar project developer challenging the application of a revised electricity tariff. It held that the project failed to meet the 180-day completion guideline stipulated in the supporting letter, making the earlier tariff inapplicable.
What did the court decide?
The appeal was dismissed with no merit found in the appellant's contention regarding the applicability of the earlier tariff rate.