(b) The Petitioner has pleaded that the total length of the new line was 14.4 KMs from the Petitioner’s project to the injection point and as per Article- 3.3 of the PPA, the Respondent-2 (the then KEB and now the KPTCL) had to bear the cost of the new line from the Project up to 5 KMs., and the cost of the new line from 5 KMs onwards up to the nearest substation had to be borne by the Petitioner. As per the letter dated 14.3.2002, the Respondent-2 had recovered Rs.1,36,21,992/- from the tariff bills during the period from 4.9.2000 to 31.5.2001 (Annexure P-41 filed with I.A.No.1/2012). Further, the Petitioner has filed a copy of the letter dated 19.4.2011 addressed by the Respondent-2 (Annexure P-42 filed with I.A.No.1/2012), informing the Petitioner that no further progress had been made in the construction of the new 110 kV Single Circuit line during the past four years, as the contractor, who was awarded the contract on 10.7.2003, was black-listed, and tendering for completion of the remaining work was in progress. The Petitioner, in the Rejoinder dated 26.6.2013, has stated that as per the PPA, the new line had to be ready before sixty days prior to the COD, and as the new line was not ready, the Petitioner was made to evacuate the Power generated through the existing feeder line, by the Respondent-2.