A.No. 380 of 2019 of Century Rayon. v. Maharashtra Electricity Regulatory Commission & Anr..
Case brief
What is this about?
The Appellate Tribunal for Electricity allowed the appeal in part, directing the adjustment of higher wheeling charges paid by an appellant since the filing of their application. The tribunal held that while retrospective relief from the MYT Order was barred, the appellant was entitled to lower charges from the date of their application due to the respondent's failure to provide infrastructure.
What did the court decide?
Adjustment of higher wheeling charges paid since the date of the application filed on 18.09.2017; no retrospective relief from MYT Order date.