Execution Petion No. 2 of 2020 in a.No. 135 of 2018 of Gmr Kamalanga Energy Limited. v. Haryana Power Purchase Centre & Ors.
Case brief
What is this about?
Appellate Tribunal allowed an interim payment of 50% of adjudicated dues to the petitioner in an execution petition filed for recovery of coal pass-through charges, directing the remaining hearing to be postponed.
What did the court decide?
Order for interim payment of 50 percent of the principal amount of Rs. 483.74 Crores claimed in the execution petition.