Appeal No. 118 of 2012 of Power Grid Corporation of India Ltd. v. Central Electricity Regulatory Commission & Ors.
Case brief
What is this about?
This appeal adjudicated the Appellant's claim for Interest During Construction (IDC) and Incidental Expenses (IEDC) regarding a transmission delay. The Tribunal held the delay was justified due to global CRGO steel shortages and prudent prioritization of critical system requirements, and allowed the appeal.
What did the court decide?
The impugned orders were set aside, and the Central Commission directed to allow the claim for IDC and IEDC after deducting liquidated damages recovered from the supplier, with consequential orders.