Karnati Ramana Reddy v. The State of Andhra Pradesh
Case brief
What is this about?
Release of pending contractor payment; writ of mandamus under Article 226; arbitrariness plea under Article 14; Roads and Buildings Department; Finance and Planning Department; Agreement DR No. 100/2022-23 dated 31.01.2023; Urgent Repairs to Ozili-Darakasthu Road Km. 7/6 to 10/6; SPSR Nellore / Tirupathi District; Section 151 CPC interlocutory application; payment directed within 16 weeks with transfer within further 4 weeks; directed amount Rs.22,38,824/- versus claimed Rs.22,38,851/-; 18% interest sought but no interest direction; no costs; single-judge oral order dated 06.01.2026.
What did the court decide?
Respondents, including Respondent No.2 (Principal Secretary, Department of Finance and Planning), directed to pay Rs.22,38,824/- to the Writ Petitioner, completing the entire administrative process within sixteen (16) weeks and transferring the amount to the petitioner's bank account within four (04) weeks thereafter; petitioner to submit bank account details within four (04) weeks. No order as to costs; interlocutory applications closed. The 18% per annum interest sought in the prayer finds no corresponding direction in the operative order.