M/s.Sri Satya Sai Constructions, v. The State of Andhra Pradesh
Case brief
What is this about?
Earnest Money Deposit; EMD reduction 2.5% to 1%; COVID-19 relief G.O.Rt.No.266 dated 15.02.2021; G.O.Rt.No.1652 dated 05.05.2025 extension; G.O.Rt.No.49 dated 13.03.2024 additional works; supplemental agreement versus fresh contract; extension of original agreement; Ekalavya Model Residential School; Tribal Welfare Department Andhra Pradesh; writ of mandamus; Article 226; Articles 14, 19, 21; illegal and arbitrary demand; Andhra Pradesh High Court at Amaravati; Nyapathy Vijay, J.; batch of six writ petitions 2025; construction contract; Seethampeta; Meliaputti; Dumbriguda; Bhamini; Anasabadra; Kurupam; Munchingiput; ACB bribery suspension of Superintendent Engineer.
What did the court decide?
Writ Petitions allowed; impugned orders (letters dated 21.10.2025 demanding 2.5% EMD) set aside; Respondents directed to extend the benefit of EMD @1% as provided in G.O.Rt.No.266 Finance (HR-V-TFR-A&L-EWF) Department dated 15.02.2021 as extended vide G.O.Rt.No.1652, Finance (FMU-WR.II) Department dated 05.05.2025, forthwith; no order as to costs; pending miscellaneous petitions stand closed.