Vunnam Janardhan Reddy v. The State of Andhra Pradesh
Case brief
What is this about?
Contractor final-bill release; admitted payment of Rs.10,59,900/- for completed works; temporary water supply arrangements for construction activity; layout Patha Tiruvuru; Tiruvuru Nagar Panchayat; Navaratnalu / Navaratnallu Pedalandariki Illu (NP) (246 Units); Housing Department; E.E. (PH) Divisional L.S. Agreement No. 65/2021-2022 dated 28.03.2022; M.Book No. 2192; Q.CC No. 35/VSP/2023-24; A.P. State Housing Corporation Ltd; Project Director; Executive Engineer Public Health Division Vijayawada; funds awaited; Article 226 mandamus; Articles 14, 16 and 21; illegal and arbitrary non-payment; disposal at admission stage; six-week timeline to verify and release payments; IA No. 1 of 2026 under Section 151 CPC; no costs; High Court of Andhra Pradesh at Amaravati; Justice Harinath.N; W.P. No. 17951 of 2026; pronounced 08.07.2026.
What did the court decide?
Writ petition disposed of at the admission stage with directions to the respondents to verify and release the payments due and payable to the petitioner as expeditiously as possible, preferably within six (06) weeks from the date of receipt of a copy of the order; no order as to costs; pending miscellaneous petitions, if any, stood closed.