M/S. Penaka Constructions v. Pradyumna,I.a.S
Contempt of Courts Act, 1971 – Sections 10 to 12
Case brief
What is this about?
Andhra Pradesh High Court at Amaravati; Contempt Case No. 5687 of 2023, decided 17.07.2026 by Justice V. Sujatha. Contempt petition under Sections 10 to 12 of the Contempt of Courts Act, 1971 by M/s. Penaka Constructions (contractor P N Srinivasulu Reddy) against Principal Secretary (R&B), Principal Secretary (Finance), District Collector Nellore and Executive Engineer (R&B) Division Nellore for non-implementation of the order dated 03.07.2023 in W.P.No.13993 of 2023 (release of Rs.15,54,889/-). Compliance recorded: Rs.15,54,889.27/- paid on 27.12.2024 vide CFMS token No.2024-160742, admitted by petitioner's counsel; contempt case closed, no costs. No precedents cited.
What did the court decide?
Contempt case closed recording compliance (payment of Rs.15,54,889.27/- on 27.12.2024 vide CFMS token No.2024-160742); no order as to costs; miscellaneous petitions, if any, stand closed as a sequel.