M/s. M.A. Waheed, Engineers v. State of Andhra Pradesh
Case brief
What is this about?
Excess payment recovery from running bills; invoice rate versus SSR rate; DI K9 pipeline supply agreements; price adjustment Clause 46; Clause 23 settlement of disputes not invoked; unilateral recovery notice set aside; Vijayawada Municipal Corporation; Vigilance & Enforcement report 11.02.2011; Government Memo 16.04.2012; Chief Engineer circular 28.04.2012; Article 226 mandamus; concluded contract terms; proof of purchase cannot override SSR rates; writ allowed without costs; earlier order dated 19.06.2018; review with 106 days delay condonation.
What did the court decide?
Impugned recovery notices dated 15.07.2013 (Rc.E9-128167/2009, Rc.E9-131610/2008, Rc.E9-131612/2008) issued by respondent No.2 set aside; writ petitions allowed without costs; pending miscellaneous petitions closed. ¶119