M/s. M.A. Waheed, Engineers & Contractors v. State of Andhra Pradesh, Rep. by its Principal Secretary
Case brief
What is this about?
Keywords: SSR rates vs invoice rate; DI K9 pipe supply; price adjustment Clause 46; Clause 23 dispute settlement; recovery from running bills; unilateral recovery; Vijayawada Municipal Corporation; Vigilance & Enforcement report 11.02.2011; Memo No.5167/E1/2011-2012 dated 16.04.2012; Chief Engineer circular 28.04.2012; Article 226 mandamus; Jakkampudi STP pumping mains. Relevant for: challenges to post-facto recovery of 'excess payment' over invoice rate where schedule of rates (SSR) was contractually fixed; limits on municipal/unilateral recovery without resorting to contractual dispute-resolution clauses; evidentiary burden on the recovering authority.
What did the court decide?
Impugned recovery notices dated 15.07.2013 (Rc.E9-128167/2009, Rc.E9-131610/2008, Rc.E9-131612/2008) set aside; writ petitions allowed without costs; pending miscellaneous petitions, if any, stand closed.