Jinnuri Phani Surya Viswa Kumar v. the State of Andhra Pradesh
Case brief
What is this about?
Andhra Pradesh High Court, Amaravati; W.P.No.33052 of 2025; decided 15.12.2025 by Justice V. Sujatha. Contractor versus State of A.P. (Principal Secretaries Irrigation and Finance, SE Dhavaleswaram Circle, EE Godavari Central Division Amalapuram, AE Ainapuram, Dy EE Amalapuram, PAO Works Accounts Vijayawada). Non-payment of admitted irrigation work bills despite Quality Control Certificates dated 3.11.2025; total Rs.7,03,161/- (Rs.3,53,561/- D.R.No.76/2024-25; Rs.3,49,600/- D.R.No.81/2024-25); non-payment attributed to non-release of budget; Article 226 mandamus; Articles 14, 21 & 300-A invoked; reliance on W.P.No.10038 of 2021 and batch (dt. 05.10.2021); direction to pay within 2 months; interest only if provided by subsisting clause in agreement/work order; IA No. 1 of 2025 under Section 151 CPC sought 24% interest; petition disposed of, no costs, MPs closed.
What did the court decide?
Respondents directed to release Rs.3,53,561/- and Rs.3,49,600/- to the petitioner in accordance with the Quality Control Certificates dated 3.11.2025 within Two (2) months from the date of receipt of a copy of the order; interest payable only under any subsisting clause in the agreement/work order; no order as to costs; pending Miscellaneous Petitions, if any, stand closed.