Sri Srinivasa and Company v. Andhra Pradesh Residential Educational Institutional Society (R)
Case brief
What is this about?
A contractor sought release of Rs.19.20 lakhs in admitted bills for balance dormitory and toilet construction work at an APR School. Following instructions confirming the bill was admitted, the High Court directed respondents to pay within four months.
What did the court decide?
Release of admitted bill amount of Rs.19.20 lakhs to petitioner within four months from date of receipt of copy of order.