N.Balaraju v. the State of Andhra Pradesh
Case brief
What is this about?
Writ petition for payment of dues under a contract for 'Neeru-Chettu' programme works. Court directed respondent authorities to complete verification within three weeks and pay the due amount within six weeks, with immediate payment liability if verification is delayed.
What did the court decide?
Direction to complete verification within three weeks and pay due amount within six weeks; immediate payment liability if verification is delayed.