The Sudha Products Rep.by its Proprietor v. Chief Managing Director
Case brief
What is this about?
This Court dismissed a writ petition challenging the quantum of electricity charges by directing the petitioner to seek redress through the Grievance Forum established under Section 42(5) of the Electricity Act, 2003, while keeping an interim arrangement in force. (Note: Judgment date 2021 appears to be a clerical error for WP filed in 2008)
What did the court decide?
Writ Petition disposed; petitioner permitted to avail remedy under Section 42(5) of Electricity Act, 2003 within two weeks; interim arrangement continues for four weeks.