Reena Kumari v. State of U.P. and 5 Others
Case brief
What is this about?
Land acquisition — sewage treatment plant, Varanasi — exchange of land or compensation — District Level Committee decision dated 29.05.2023 — Government Order dated 12.05.2016 — non-implementation by U.P. Jal Nigam (Rural) — demarcation 30.07.2023 — mandamus — direction to Chief Engineer (Ganga) and Project Manager, Ganga Pollution Control Unit-II — personal appearance to show cause — subsequent purchaser — Section 4 Land Acquisition Act, 1894 — Kargil War Hero — interim directions — matter pending, listed 16.02.2026.
What did the court decide?
Interim direction issued: the Chief Engineer (Ganga), U.P. Jal Nigam (Rural) and the Project Manager, Ganga Pollution Control Unit-II, U.P. Jal Nigam (Rural), Varanasi were directed to look into the matter and expedite settlement of land in favour of the petitioner before the next date, failing which both officers shall appear in Court to show cause regarding their conduct; the writ petition was not finally decided and was directed to be listed again as fresh on 16.02.2026.