M/S Gayatri Hospitality and Realcon Ltd. Thru. Auth. Signatory Sri Suraj Mishra v. State of U.P.Thru.Addl.Chief Secy.Deptt.of Infrastructure and Industrail Development,Lko.and 2 Ors.
Case brief
What is this about?
Allahabad High Court Lucknow Bench Writ-C 4159 of 2026; GNIDA Greater Noida Industrial Development Authority; land allotment 2011 delayed possession 01.09.2017; zero period benefit; revisional order 02.08.2023 State Government UP Infrastructure Industrial Development; Government Order 21.12.2023 Covid period benefits; review application withdrawn; demand order 24.02.2024 challenged; interim stay of coercive action; counter affidavit entitlement; listing 12.05.2026 top ten; Alok Mathur Amitabh Kumar Rai; builder real estate development U.P.
What did the court decide?
Interim directions only: (i) one week's time to respondent No.3 (GNIDA) to seek instructions/file a short counter affidavit indicating petitioner's entitlement; (ii) case to be listed on 12.05.2026 amongst top ten cases; (iii) no coercive action against the petitioner till the next date of listing