M/S Adeeba Naaz Contractor Thru. Proprietor Mr. Iftikhar Danish v. State of U.P. Thru. Prin. Secy. Deptt. of Minority Welfare and Waqf Lko. and 2 Others
Case brief
What is this about?
Blacklisting; debarment for indefinite period impermissible; show cause notice condition precedent for blacklisting; grounds to be disclosed in show cause notice; principles of natural justice; civil consequences; ex-parte blacklisting order quashed; Article 226 writ certiorari; U.P. Waqf Vikas Nigam Limited; Executive Engineer; Tender Notice No. 4715; Government Girls Degree College Najibabad District Bijnor; termination of contract; non-payment of dues; arbitration clause in tender documents; Kulja Industries (2014) 14 SCC 731; Ragunath Thakur (1989) 1 SCC 229; Gorkha Security Services (2014) 9 SCC 105; UMC Technology MANU/SC/0858/2020 AIR 2021 SC 166; M/s Hi Tech Pipe Writ-C No. 11037 of 2024; Allahabad High Court Lucknow Bench.
What did the court decide?
The blacklisting portion of the impugned order dated 08.01.2025 was quashed and set aside as arbitrary and violative of natural justice; the petitioner was left at liberty to proceed under the arbitration clause in the tender documents for termination of contract and non-payment of dues; writ petition disposed of with the above directions.