Lucknow Developmet Authority, Lucknow Thru. Secy., v. Ram Sevak and Others
Case brief
What is this about?
Condonation of delay; insufficient cause; bureaucratic delay by State instrumentality; parity between government and private litigants; Shivamma (Dead) by LRs v. Karnataka Housing Board, MANU/SC/1262/2025; Section 5 Limitation Act; Section 74 RFCTLARR Act 2013; Section 18 Land Acquisition Act 1984; compensation enhancement Rs. 18.36 to Rs. 115 per square foot; Amar Shaheed Path Gomtinagar Vistaar Phase-1A, Village Ujariwayon, Lucknow; Lucknow Development Authority; FAPLD No. 137 of 2024; appeal dismissed for delay and laches; Prashant Kumar, J.; Allahabad High Court Lucknow Bench.
What did the court decide?
None; the delay condonation application (and the subsequent application) was rejected and the appeal was dismissed. ¶51