Managing Director, U.P. Rajkiya Niraman Nigam Ltd. Gomti Nagar Lko. and 2 Others v. M/S Universal Construction 122/313 Shastri Nagar Kanpur U.P.
Case brief
What is this about?
Allahabad High Court (Lucknow Bench), Court No. 2, order of January 6, 2026 in Section 37 Arbitration and Conciliation Act 1996 appeal No. - 54 of 2025; appellants: Managing Director, U.P. Rajkiya Niraman Nigam Ltd. and 2 others (counsel: Gaurav Mehrotra, Senior Advocate; Madhur Jhavar); respondent: M/S Universal Construction, Kanpur (counsel: Ankit Kumar Pandey; Hairdaya Narain Tiwari). Purely procedural: time sought to file objections to condonation-of-delay and interim-relief applications; objections on maintainability of the appeal served on appellant's counsel with reply due by next listing; case adjourned to the following week. Judges: Sangeeta Chandra and Amitabh Kumar Rai. No merits adjudicated.