The Chief Engineer, U.P. PWD World Bank Projects Thru. Superintending Engineer, P.W.D. Mathura v. M/S. D.S. Constructions Ltd., New Delhi
Case brief
What is this about?
Section 37 appeal; legitimate expectation; public law principles in private law contract disputes; pre-bid meeting assurances not part of contract terms; interpretation of contract via inter-party correspondence; admission of appeal and stay of arbitral award; Commercial Tribunal judgment under Section 34; deposit Rs. 5 crore FDR per appeal; Section 36 pre-deposit condition; interest pendente lite and future interest; MMTC Limited v. Vedanta Limited; International Seaport Dredging v. Kamarajar Port; Board of Control for Cricket in India v. Deccan Chronicle Holdings; Shyama Prasad Mookherjee Port v. Universal Sea Port; State Highway No.47 Bijnore-Nazibabad; U.P. PWD World Bank Projects; D.S. Constructions Ltd.; exemption certificate customs excise duty; execution proceedings Article 227; interim order 16.08.2017.
What did the court decide?
Appeal admitted at admission stage; further operation of the impugned Award and judgment of the Commercial Tribunal stayed till the next date of listing (10.02.2026); appellant directed to deposit Rs. 5 crore in each of the connected appeals in separate FDR accounts in a nationalised bank, subject to final order; counter affidavit/objections on merits permitted; Commercial Court and Arbitral Tribunal records to be summoned, steps to be taken by appellant within one week. Final adjudication of the claim expressly left open.