Allahabad High Court, Lucknow Bench, Court No. 8; Matters Under Article 227 No. 1167 of 2026; Taurant Projects Ltd. v. Green Gas Ltd.; interim order dated 16.03.2026 by Manish Kumar, J.; challenge to orders dated 06.12.2025 and 13.04.2022 of Commercial Court -II, Lucknow in Arbitration Case No. 70 of 2024; notice issued both ways; Dasti notice directed; listed week commencing 30.03.2026; no final decision, no cases or statutes adjudicated.
What did the court decide?
Interim directions only: notice ordered to issue both ways; three days' time granted to the petitioner for filing steps; Office directed to provide 'Dasti Notice' for service upon respondents no.2 and 3; petitioner permitted to file affidavit of service by the next date; case listed in the week commencing 30.03.2026 as fresh. No merits determination made. ¶11