Universal Engineering Equipments Corporation Thru. Proprietor Sri Rohit Uppal and Another v. State of U.P. Thru. Its Prin. Secy. Deptt. of Technical Education Deptt. Lko. and 4 Others
Case brief
What is this about?
Tender eligibility dispute — turnover criterion (average turnover of Rs.54 crores), EMD exemption claim timing, warranty discrepancy (annexure at page 115 vs. warranty submitted on 21.08.2025); pre-bid clarification uploaded on portal; stay refused with protection that action taken abides by final result of writ petition; counter affidavit within two weeks; rejoinder within three days; listed 26.09.2025; Allahabad High Court Lucknow Bench; WRIT - C No. 8445 of 2025; Rajan Roy and Manjive Shukla, JJ.; decided September 4, 2025.
What did the court decide?
Interim order only: stay declined, but any action taken shall abide by the final result of the writ petition; counter affidavit directed within two weeks, rejoinder affidavit (if any) within three days thereafter, and the case listed on 26.09.2025. ¶11