Ramkrisna Gupta and 2 Others v. Executive Engineer and Project Director, National Highway Khand, Public Work Department and Another
Case brief
What is this about?
Petitioners whose land was acquired for a national highway sought a rehabilitation and resettlement award under the 2013 Act. Following earlier orders of this Court, the writ petition was disposed of directing the Competent Authority under the National Highways Act, 1956 to examine R&R claims per Chapter V of the 2013 Act within twelve weeks.
What did the court decide?
Competent Authority under the National Highways Act, 1956 directed to examine R&R claims and take decision per Chapter V of the 2013 Act within twelve weeks of communication of the order.