Dinesh Gandhi v. State of U.P. Thru. Prin. Secy. Deptt. Revenue Sectt. Lko. and 4 Others
Case brief
What is this about?
Writ petition WRIT-C 366 of 2025, Lucknow Bench, order dt. 22.1.2025; illegal construction of top floor by opposite party no. 5; compounding of unauthorised construction; compounding order not on record; completion certificate withheld by Lucknow Development Authority (LDA); Section 15A U.P. Urban Planning and Development Act, 1973; prayer to issue completion certificate ignoring top floor pending compounding proceedings; directions to official respondents to file counter affidavit; notice to opposite party no. 5; all pleas left open; interim directions only, no final adjudication.
What did the court decide?
Interim directions only, matter kept pending: official respondents to bring the compounding order on record and respond to the writ petition; notice to Opposite Party No.5; all pleas left open; LDA to examine and, if permissible, consider issuance of completion certificate ignoring the top floor and report in the counter affidavit.