M/S Dinesh Kumar Thru. Its Sole Prop. Dinesh Kumar v. State of U.P. Thru. Its Prin.Secy. Deptt. of Public Works, Lko and 5 Others
Case brief
What is this about?
Two writ petitions challenge tender finalisation in favour of opposite party no.6 whose balancesheet was held false by the district level committee. The court found the headquarter level committee ignored bid document clauses and directed the Engineer-in-Chief to institute an inquiry, restrained issue of work order, and permitted a fresh decision.
What did the court decide?
Work order to opposite party no.6 restrained; inquiry ordered; fresh decision permitted without prejudice.