Satya Prakash Katara v. Junior Engineer Dakshinnanchal Vidyut Vitram Nigam Ltd. and 3 Others
Case brief
What is this about?
Satya Prakash Katara v. Junior Engineer, Dakshinnanchal Vidyut Vitram Nigam Ltd. & 3 Others; WRIT - C No. 18215 of 2025; Allahabad High Court, order dated 8.7.2025; electricity arrears and two-year recovery bar under Clause 6.15, U.P. Electricity Supply Code, 2005; reconnection procedure Clause 4.39; installment facility Clause 6.14 (Executive Engineer/DGM/GM, maximum 2-4 monthly installments, first installment not less than 40%, Rs.10,000/- post-dated cheque threshold); Permanent Lok Adalat, Mathura order dated 15.02.2025 partly allowing claim left undisturbed; direction to provide new connection on deposit of Rs.40,000/- within one month and balance in three monthly installments; writ petition disposed of finally.
What did the court decide?
New electricity connection to be provided upon deposit of Rs.40,000/- within one month, followed by reconnection; remaining dues payable in three easy monthly installments; impugned Permanent Lok Adalat order left undisturbed.