M/S Ridhi Sidhi Enterprises v. State of Up and 3 Others
Case brief
What is this about?
The petitioner challenged the rejection of its claim for balance payment by the Kanpur Development Authority. The court noted that the work contract lacked an arbitration clause and the dispute involved complex factual questions regarding work performed. The court declined to decide the merits, directing the petitioner to approach a competent civil court.