U.P. State Industrial Development Authority Thru. Project Officer v. Manoj Awasthi
Case brief
What is this about?
UPSIDA appeals a RERA Tribunal order awarding compensation for delayed plot possession. Court admits the appeal on two substantial questions of law concerning tribunal's deposit-refund powers and entitlement to interest absent prescribed Rule 15 rates; grants interim measure keeping untransmitted amounts in an interest-bearing account.
What did the court decide?
Appeal admitted on two substantial questions of law; three weeks for objections; interim direction to keep untransmitted appellate-order amount in interest-bearing account with Tribunal.