E-City Entertainment India Pvt. Ltd. Thru. Its Authorized Rpresentative v. Moksh Innovations Inc. a Sole Propriety Concern Thru. Proprietor, Mr. Akshay Kumar Thakur
Case brief
What is this about?
Petition under Article 227 sought a direction for early disposal of an application under Section 36 for execution of an arbitral award, with the related Section 34 challenge also pending before Commercial Court No.2, Lucknow. With consent, the court directed decision of the Section 34 application within four months.
What did the court decide?
Direction to Commercial Court No.2, Lucknow to decide the Section 34 application within four months; liberty to seek expedition of Section 36 execution thereafter.