M/S Aditya Construction a Partnership Firm , Lko. U.P. Thru. Partner Sri Akhil Bansal v. Ansal Properties and Infrastructure Ltd. Lko. Thru. Managing Director
Arbitration and Conciliation Act, 1996 – Sections 37, 9 and 17
Case brief
What is this about?
Allahabad High Court, Lucknow Bench (Chief Justice's Court), Division Bench of Arun Bhansali, Chief Justice and Jaspreet Singh, J.; Neutral Citation 2024:AHC-LKO:70169-DB; decision dated 18.10.2024. Appeal under Section 37 of the Arbitration and Conciliation Act 1996 (No. 9 of 2024) by M/S Aditya Construction (through partner Akhil Bansal) against Ansal Properties And Infrastructure Ltd., challenging dismissal of its Section 9 interim-relief application by Commercial Court No. 1, Lucknow (order dated 03.02.2024). Appeal disposed of on the joint prayer of counsel as the Arbitrator stood appointed and the appellant's Section 17 interim-relief application was pending before the Arbitrator. Statutes: Sections 37, 9, 17 of the Arbitration and Conciliation Act, 1996. No precedents cited or decided on merits.
What did the court decide?
None on merits; the appeal was disposed of in view of the appointment of the Arbitrator and the pendency of the appellant's application under Section 17 of the Act for interim relief before the Arbitrator.