Vishwas Singh v. State of U.P. and Another
Case brief
What is this about?
The High Court granted interim relief preventing coercive recovery measures for two months while directing the petitioner to file objections to the provisional assessment notice and checking report. The court mandated a reasoned decision by the Executive Engineer within four weeks.
What did the court decide?
No coercive measure for two months; direction to submit objections to Executive Engineer; direction to decide within four weeks.