Apace Buildtech Pvt. Ltd. Having Its Office at D-53 Thru. Its Authorised Signatory v. State of U.P Thru. Deptt. of Industrial Development Thru. Addl. Chief Secy. and 2 Others
Case brief
What is this about?
The court held that a revision petition against a demand notice was not maintainable as the notice was not a disposed order. The petition to quash the notice was dismissed because reviewing the notice would require deciding the merits of the agreement. However, the writ for a direction regarding the Zero Period Policy was allowed.
What did the court decide?
The writ petition was disposed of with a direction to the New Okhla Industrial Development Authority to take a reasoned decision on the petitioner's claim for Zero Period Policy within two months.