Meerut Development Authority v. Champo Devi and 3 Others
Case brief
What is this about?
The High Court allowed first appeals filed by the Meerut Development Authority. The Court held that since the agreed compromise rate of Rs.165 per sq. yard included solatium, no additional solatium could be awarded over solatium. The Court also held that the issue regarding the impleadment of Jaswant Sugar Mill Ltd. was not agitable. Catchwords: Land Acquisition, Solatium, Compensation.
What did the court decide?
The awarded amount of Rs.165 per sq. yard is directed to be treated as inclusive of statutory interest and solatium, with no additional solatium or other benefits payable under Section 23 of the Act.